From signing the contract to a running system typically takes two to four months – the installation itself only two to four working days. Your active effort is concentrated at the beginning: checking the roof, comparing quotes, deciding. After that, a good specialist company will largely take over the paperwork – with one exception, which belongs before construction begins. (As of: July 2026)
In this chapter, you'll learn
- what the path from idea to running system looks like – and who does which part;
- where the time really goes (hint: not on the roof);
- which single deadline cannot be made up for.
The path in three minutes
Your part is at the beginning. The first three stages you need to do yourself – together a few hours: checking your own roof (ten minutes on sonnendach.ch, plus the question of what consumers will be added), getting quotes from two to three regional specialist companies with the same key data, and making the decision in one evening. How to cleanly compare quotes has its own craft – the comparison checklist takes the guesswork out of it.
From the signature onwards, the work changes sides. Notification procedure with the municipality, connection request to the grid operator, scheduling with scaffolding and installation team: This is the specialist company's business and runs in parallel in the background over weeks. The installation itself is the shortest part of the whole project – two to four working days on the roof, your presence is not necessary. After that, the grid operator changes the measurement, the independent inspection checks the installation, and the system goes onto the grid.
Where the time really goes: rarely on the technology, almost always at the interfaces – deadlines of the grid operator, scaffolding coordination, in core zones the clarification with the municipality. That is why two to four months from the signature to the running system is the realistic timeframe, even if work on the roof only takes days.
The one exception in the paperwork that is yours: If your municipality pays an incentive contribution, this application must be submitted before construction begins – the only step in the whole process that cannot be made up for later. The one-off feed-in incentive of the federal government, on the other hand, is applied for in a relaxed manner after commissioning, usually by the specialist company; you are left with the tax folder at the end. You know the details about this from Chapter 5.
Finally, the handover moment: This includes system documentation, introduction to monitoring and the warranty documents. A specialist company that hands over these three things without being asked also has the rest of the path under control.
Go deeper on this topic
Read more from the guide: – In 7 steps to your own solar system — the complete process with timetable table – Buying a solar system in Switzerland: the buying guide — from choosing a provider to the contract – Comparing solar quotes — the checklist for the decision – Pronovo registration step by step — what happens after commissioning
### Keep in mind Your effort lies in the first three steps, the waiting time at the interfaces – and the municipality application is the only one that must be made before construction begins.
In brief
How long does it take from the quote to the running system? From signature to the system on the grid typically two to four months – depending on the season, municipality and grid operator. The installation itself only takes two to four working days; the rest is planning, registrations and deadlines in the background.
Do I need a building permit? For most roof systems, the simpler notification procedure with the municipality is sufficient – the specialist company takes care of this. It is different in core zones and for protected objects: there a permit is required, and the clarification takes correspondingly longer. The specialist company knows what applies after a look at the zone.
Do I have to be at home during the installation? No – access to the meter box and utility room is sufficient. Your presence is useful at the handover at the end: there you receive documentation, monitoring instruction and warranty documents, and there you ask the questions that have accumulated during the installation.
Solar-Guide: ← Chapter 7: Battery, heat pump, e-car · To the guide overview · Chapter 9: After the installation →
Free initial consultation
Ready for step 2?
The path begins with a quote: free of charge, without obligation and with all items transparently broken down – from the site visit to the timetable for your roof.
Prefer to talk? +41 78 830 83 35
Have a photovoltaic system installed →
Swissolar-certified specialist company · ESTI installation authorisation (Art. 14 NIV) · in Zurich since 2017 · over 150 systems completed · a personal answer from the specialist company, no call centre
Sources: EnergieSchweiz, Pronovo AG, grid operator processes; process and guideline values taken 1:1 from the step-by-step guide (V30).
Last updated: 9 July 2026 · Author: ecoEn editorial team